A Case of First Impression: Duty to Defend Construction Defect Claims in Prelitigation Proceedings

In response to an onslaught of construction defect cases, California enacted statutory procedures to encourage settlement of claims before a lawsuit is even filed. But those procedures usually involve attorneys and experts, and they cost money, so are insurance companies obligated to pay the defense costs even though a lawsuit has not officially been filed? In a case of first impression, a California Court of Appeal has answered that question in the affirmative.

 In Clarendon America Insurance Company v StarNet Insurance Co. (2010) Cal App 4th, Centex Homes was the developer of a residential development in Simi Valley, California known as Westwood Ranch. In July 2006, the Westwood Ranch Homeowners Association served a notice of commencement of legal proceedings pursuant to California Civil Code section 1375 on Centex that set forth a list of alleged construction defects at Westwood Ranch. This step was taken in compliance with the Calderon Act which requires that developers and homeowners associations engage in a prelitigation effort to settle construction defect claims. If the claims can nor be settled, the homeowners association is then authorized to file a lawsuit.

StarNet Insurance had issued two successive CGL policies to one of Centex’s subcontractors on the project, and Clarendon America Insurance had issued a CGL policy to another subcontractor. Centex was a named additional insured on the policies issued by both carriers.

In December 2007, Centex filed a complaint against Clarendon seeking payment of defense fees and costs incurred in defending against the construction defect claims in the prelitigation proceeding known in California as the Calderon Process. Clarendon filed a cross-complaint against the other insurers, including StarNet, seeking a declaration they were obligated to provide Centex a defense and/or coverage. In the first amended cross-complaint, Clarendon sought indemnity, declaratory relief, and contribution from the additional insurers. Clarendon reached settlements with all of the other CGL insurers except StarNet.

StarNet moved for summary judgment asserting the prelitigation process did not constitute a "suit" within the meaning of the defense agreement in the StarNet CGL policies. The trial court denied the motion, holding the prelitigation procedure “ is a civil proceeding in which damages are alleged and therefore falls within the StarNet CGL policies' definition of ‘suit’…Additionally, the definition of 'suit' also includes alternative dispute resolution procedures to which the insured submits with the insurer's consent…Thus, even if the Calderon process is not considered to be a 'civil proceeding' if that phrase is narrowly interpreted to mean 'court action[,'] but rather is considered an 'alternative dispute resolution proceeding[',] there is a question of fact as to whether or not Star[N]et has a duty to defend once the Calderon process has begun."

After analyzing the language of StarNet’s policy according to the standard rules of insurance policy interpretation, the Court of Appeal made this important observation:

The Calderon Process is more than a prelitigation alternative dispute resolution requirement: It is part and parcel of construction or design defect litigation initiated by an association and, as such, cannot be divorced from a subsequent complaint.

In affirming the trial court’s ruling, the Court stated, “The function and significance of the Calderon Process in construction or design defect litigation, and the StarNet CGL policies' definition of "suit" to include civil proceeding, lead to the reasonable inference the parties' intended StarNet would have a duty to defend the insured in the Calderon Process. Extending the duty to defend to the Calderon Process is therefore consistent with a hypothetical insured's reasonable expectations.”

This is good news for contractors, developers and, of course, homeowner associations. Hopefully CGL carriers will be more forthcoming in participating in prelitigation procedures such as the Calderon Process in California. This holding should lead to more prelitigation resolutions of construction defect cases and facilitate the public policy reasons for the enacting such laws.

Study Shows Attorney Overconfidence is a Barrier to the Efficient Resolution of Disputes

 

Barriers to conflict resolution are many, and much has been written about them. In Insightful or Wishful: Lawyer’s Ability to Predict Case Outcomes, a legal studies research paper for the new law school at the University of California at Irvine, noted American psychologist Elizabeth Loftus addresses another barrier to settlement that we lawyers are loath to admit: overconfidence. Indeed, the “saber rattling” of mediation colloquy can sound like the dramatic dialogue out of a Star Wars movie:

Luke: Soon I’ll be dead and you with me. Translated: We’re spending a boatload of money litigating this case but you will run out of money before we do.

The Emperor: [laughing] Perhaps you refer to the eminent attack of your rebel fleet? Yes, I assure you, we are quite safe from your friends here. Translated: Perhaps you refer to your army of expensive expert witnesses. They are no threat to us. I assure you we are prepared to destroy their testimony.

Luke: Your overconfidence is your weakness. Translated: Your overconfidence is your weakness.

The Emperor: Your faith in your friends is yours. Translated: Don’t count on the jury to bail you out of this one.

But lawyers are supposed to be confident, right? Yes, but there is a difference between having confidence and the courage of your convictions and overconfidence and the consequences of poor judgment. In an amusing analogy, Professor Loftus compares and contrasts lawyers and weather forecasters.

First, meteorologists cannot in any way influence the outcome of their predictions. Nothing they do can make it rain. Lawyers, on the other hand, can behave in ways that influence the case outcome. Because they have this opportunity, they may overestimate their own capacity and neglect the importance of factors beyond their control. Second, lawyers have a much keener interest in the goals of their predictions than do meteorologists. Because of this, lawyers might be susceptible to over optimism and wishful thinking.

The central focus of Professor Loftus’ study is the degree of accuracy in lawyers’ forecasts of case outcomes. To read the entire research paper click here. (PDF)  Meanwhile, the following quotes provide a glimpse of her insightful observations :

In summary, whether lawyers can accurately predict the outcome of a case has practical consequences in at least three areas: (a) the lawyer’s professional reputation and financial success; (b) the satisfaction of the client; and (c) the justice environment as a whole. Litigation is risky, time consuming, and expensive.

The consequences of judgmental errors by lawyers can be costly for lawyers and their clients, as well as an unnecessary burden on an already overloaded justice system. Ultimately, a lawyer’s repute is based on successful calculations of case outcome. A lawyer who advises clients to pursue litigation without delivering a successful outcome will not have clients for long. Likewise, a client will be most satisfied with a lawyer who is accurate and realistic when detailing the potential outcomes of the case. At the end of the day, it is the accurate predictions of the lawyer that enable the justice system to function smoothly without the load of cases that were not appropriately vetted by the lawyers.

A lawyer who cannot accurately predict the outcome of a case or who does not thoroughly and efficiently appreciate the litigation risks may ignore alternatives to trial and advise the client to reject reasonable settlement offers. A lawyer who underestimates potential outcomes may advise the client to accept an unreasonably lower amount in settlement than is warranted.

Another factor that might affect the realism of lawyers’ assessments of future goals is perception of control. The extent to which an individual believes he or she can take steps to increase the likelihood of a desirable outcome has been shown to bias confidence estimates in those outcomes. When an event is perceived to be controllable, overconfidence is likely. This bias is linked to what Langer (1975) called an illusion of control, defined as “an expectancy of a personal success probability inappropriately higher than the objective probability would warrant”.

Lawyers frequently made substantial judgmental errors, showing a proclivity to over optimism. The most biased estimates were expressed with very high initial confidence: In these instances, lawyers were extremely overconfident. These findings are consistent with a large body of literature documenting overconfidence in a range of judgments.

With regard to gender, we replicated results obtained by Malsch (1990) that female lawyers were better calibrated than their male colleagues. Male practitioners were more overconfident than female practitioners. These findings are in line with gender differences observed in research on metacognition.

One implication of the present findings is that lawyer performance can be improved by implementing case management strategies that take into account the potential overconfidence biases of the litigators.Case consultations with legal peers can take place informally. For example, in many legal firms, regular meetings are held where cases are periodically reviewed so that the partners can manage the caseload efficiently and ethically. These meetings provide ideal opportunities to obtain objective opinions from other legal professionals in the form of third-party feedback about the strengths and weaknesses of a case and the likelihood that the stated goals can be achieved.

 

This study shows that lawyers can be too confident. When lawyers do not fully assess the risks or acknowledge certain aspects of the case that may be beyond their control, over-(and under) valuations can happen, making settlement impossible. Objectivity requires lawyers to walk a fine line, some would call it a high wire balancing act, between zealous advocacy and wise counsel. Indeed, wisdom is the safety net that keeps litigators from crashing to the earth.

May the Force be with you.

 

 

A NEW CALIFORNIA SUPREME COURT OPINION AFFECTING THE CONSTRUCTION INDUSTRY: TO DISCLOSE OR NOT DISCLOSE IS NO LONGER THE QUESTION

Construction claims for non-disclosure on public works projects got a little easier to prosecute yesterday with the publication of the California Supreme Court’s decision in Los Angeles Unified School District v. Hayward Construction. (PDF) The importance of this case is reflected by the list of attorneys who represented the parties, a veritable Who's Who in the legal community.The contractor and surety were represented by veteran construction lawyers John Immordino of Wilson Elser and Joseph Miller of Montelone & McCrory. The school district was likewise well represented by its General Counsel, Roberta Fesler, Gregory Bergman of Bergman & Darcey and lawyers at Jones Day, including Ellwood Lui, a former associate justice of the California Court of Appeal, Second Appellate District, Division 3..

In the Hayward Construction case, and for the first time, the Court was asked to resolve a construction dispute brought solely on a theory of non-disclosure during the bidding phase of a project. The question was whether a contractor can recover extra costs of construction when the plans and specifications are correct, but the public entity failed to disclose information in its possession that materially affected the cost of performance.

The case is also important because it resolves conflicting opinions between four of the California Courts of Appeal. One Appellate Court, followed by the trial court in the Hayward Construction case, held that to recover for nondisclosure, the contractor must show the public entity affirmatively misrepresented or intentionally concealed material facts that rendered the furnished information misleading. Another Court of Appeal held a contractor need not prove an "affirmative fraudulent intent to conceal" when disclosure would have eliminated or materially qualified the misleading effect of facts disclosed. A third Appellate Court suggested that the careless failure to disclose information may allow recovery if the public entity possessed superior knowledge inaccessible to the contractor. And the Appellate Court in the Hayward Construction case broadly held that a contractor need show only that the public entity knew material facts concerning the project that would affect the contractor's bid or performance and failed to disclose those facts to the contractor.

SUMMARY OF THE FACTS

Hayward entered into a contract with a school district to complete the work of the original contractor who was in default. The scope of the work was based on a 108 page “pre-punch list” and required Haywood to correct the defective, missing and incomplete work on a time and material basis up to a guaranteed maximum price.

Shortly after beginning work, Hayward informed the district there were significant deficiencies in the existing work that had not been noted on the pre-punch list and could not have been detected by a visual inspection. As a result, Hayward made a claim for extra compensation to perform this additional work. The district then sued Hayward and its surety and Hayward filed a cross-complaint against the district, alleging misrepresentation and concealment. In support of these theories, Hayward alleged the district failed to disclose the extent of the defects in the existing construction, and failed to disclose information that would have put Hayward on notice that some of its assumptions about the scope of the required work were erroneous.

After losing a motion for judgment of the pleadings in the trial court, Hayward won at the Court of Appeal, and then the school district appealed to the California Supreme Court.

THE COURT'S DECISION

The California Supreme Court affirmed but narrowed the court of appeal’s opinion in Hayward Construction, holding that a contractor need not prove an affirmative fraudulent intent to conceal. Rather a public entity may be required to provide extra compensation if it knew, but failed to disclose, material facts that would affect the contractor's bid or performance.

In narrowing the Court of Appeal's opinion, the California Supreme Court stated:

[W]e conclude the Court of Appeal's rule was, in turn, overbroad in suggesting that recovery may be had for any failure to disclose material information. Rather, we hold that a contractor on a public works contract may be entitled to relief for a public entity's nondisclosure in the following limited circumstances: (1) the contractor submitted its bid or undertook to perform without material information that affected performance costs; (2) the public entity was in possession of the information and was aware the contractor had no knowledge of, nor any reason to obtain, such information; (3) any contract specifications or other information furnished by the public entity to the contractor misled the contractor or did not put it on notice to inquire; and (4) the public entity failed to provide the relevant information.

The Court noted the circumstances affecting recovery may include, but are not limited to, positive warranties or disclaimers made by either party, the information provided by the plans and specifications and related documents, the difficulty of detecting the condition in question, any time constraints the public entity imposed on proposed bidders, and any unwarranted assumptions made by the contractor. The public entity may not be held liable for failing to disclose information a reasonable contractor in like circumstances would or should have discovered on its own, but may be found liable when the totality of the circumstances is such that the public entity knows, or has reason to know, a responsible contractor acting diligently would be unlikely to discover the condition that materially increased the cost of performance.

The is an important case in the construction industry. The risks of the bidding process became a little less risky. The uphill battle for contractors claiming extra work for unknown conditions got a little easier. They will still have to overcome the Spearin rule stated by the U.S. Supreme Court nearly a hundred years ago, that a contractor can not avoid its contractual obligations or seek additional compensation for performing them merely because unanticipated circumstances are encountered. Contractors will still have to get past disclaimers and other contractual language that attempt to place the burden of unanticipated conditions on them. But the Hayward Construction case now gives them some relief when making a claim for non-disclosure: they do not have to prove an intent to defraud; only a failure to disclose material facts that would affect the contractor's bid or performance.When such a claim arises, the contractor should make a demand for all documents in the owner’s possession, custody or control relating to the conditions of the project.

As for the parties in the Hayward Construction case, they are back in the trial court preparing for trial.

NOTE: Nine amicus curiae (friends of the court) briefs were filed in the Supreme Court of California on behalf of various organizations. Such briefs are often filed in appeals concerning issues of broad public interest. Four amicus curiae briefs were filed on behalf of various construction industry organizations, including the Associated General Contractors Association of California and the American Subcontractors Association. Five amicus curiae briefs were filed on behalf of various governmental organizations, including the California School Boards Association and The League of California Cities. The filing of these briefs by outstanding lawyers and law firms is another indication of the importance of the Hayward Construction case to the respective interests of construction professionals and public entities in California.

 

 

 .

 

 

 

 

A New Case Upholding Customized Dispute Resolution Provisions

It is an interesting paradox that construction professionals who devote their lives to building unique structures according to customized plans generally use "cookie cutter" form contracts to govern the duties and obligations of the parties. When a construction dispute arises, most construction professionals and their lawyers will spend many hours scrutinizing the contract documents to analyze their rights. Since so much time is spent evaluating the contract after the dispute, shouldn't there be at least an equal amount of time and thought put into it before the project begins? Instead of standard cookie cutter provisions, doesn't it make sense to think about the risks of the project and clearly define what will happen in the event of a dispute?  I have been preaching this sermon for many years, and recently posted an article on the subject called, Resolve Construction Disputes More Efficiently With Customized ADR Provisions.

A new case in California  (PDF) illustrates the benefit of customized contract provisions related to dispute resolution. The case involved the proposed development of a parcel of property and a contingent lease for a drug store build-out for Rite Aid. Here is the smart part of what happened: the lease agreement did not have the standard "prevailing party" language in the event of a dispute. Instead the lease stated that the prevailing party is entitled to "reasonable expenses," and then listed what the parties meant by that term: attorney fees, court costs, witness and expert fees.

The developer won the case and asked the court to award reasonable expenses including attorney fees and expert witness fees. Rite Aid challenged the developers request for $83,000 for expert witness fees in a motion to tax costs. The trial court denied the motion and Rite Aid appealed the judgment in favor of the developer, including the award of expert witness fees.

The California Court of Appeal affirmed the award of expert witness fees, holding that the the lease expressly called for them as an item of cost. The Court gave deference to the fact that this was a customized provision negotiated by sophisticated parties:

This does not mean-and we do not hold-that expert witness fees are recoverable in every case where "costs" are merely mentioned in a contract. A general cost provision should be interpreted according to the established statutory definition. But where sophisticated parties knowingly and intentionally negotiate a broader standard into their contract-and particularly where, as here, that standard specifically includes "witness and expert fees"-the intent of the parties should be upheld by the court. (Emphasis added.)

In most states, there are other ways to obtain an award of expert witness fees. I wrote about them in a post entitled, Settlement Negotiations: Don't Get Smacked By The Statutory Stick. But statutory awards of expert fees are discretionary awards made by the trial court after certain facts are established to the satisfaction of the judge. This Rite Aid case, on the other hand, provides a blue print for construction professionals who want to clearly define what will happen to the losing party in the event of a dispute rather than hoping for the favorable discretion of the trial court.